What it says
What this says
As at Fri 9 Oct 2026Final v1 onboarding plan for Copperlane Payroll's B-Glass, four weeks from 1 June 2025, with 15 licensed users and four connectors. It states no price, availability or P1 response figures. It names Hamza Akhtar and Daniel Okafor as the BG-Demo team.
What it is: a delivery plan in four phases (Foundation, Configuration, Testing and Refinement, Go-Live and Handover), filed as final. Hamza Akhtar owns the first three phases and Daniel Okafor owns go-live and handover.
Commits: BG-Demo to a four-week implementation, "All four connectors operational and data indexed" in Week Two, and "Brain live to all 15 users" in Week Four. Post-implementation, Daniel is the dedicated Customer Success Manager with a six-monthly check-in.
Unusual: nothing off the standard terms. The plan has no signatures, so it is not a contract or order form.
Not settled: the plan states no price, service levels, connector delivery dates in days, or renewal date. It does not show whether go-live happened on schedule.
As found in this document
As at Fri 9 Oct 2026- Date start1 Jun 2025Source: the AI read of this record
- Implementation durationto be completed over four weeks starting 1 June 2025Source: the AI read of this record
- Week Two milestoneAll four connectors operational and data indexedSource: the AI read of this record
- Week Four milestoneBrain live to all 15 usersSource: the AI read of this record
- Data refreshData refresh happening on schedule each business nightSource: the AI read of this record
- Check-insix-monthly check-in to review adoption and valueSource: the AI read of this record
Body
Copperlane Payroll, Onboarding Plan
Version 1 (Final)
Overview
This plan outlines the implementation of B-Glass at Copperlane Payroll, to be completed over four weeks starting 1 June 2025.
Implementation Team
| Role | Name | Organisation |
|---|---|---|
| Implementation Consultant | Hamza Akhtar | BG-Demo |
| Customer Success Manager | Daniel Okafor | BG-Demo |
Phase 1: Foundation
Timeframe: Week One, starting 1 June 2025
Objectives:
- Confirm data sources and system access
- Provision and configure Snowflake account
- Establish initial connectors to payroll, client and invoicing data
- Conduct team orientation
Owner: Hamza Akhtar
Milestones:
- Snowflake instance deployed
- First two connectors live
- Access provisioned for all users
Phase 2: Configuration
Timeframe: Week Two (June 2025)
Objectives:
- Complete connector setup and data validation
- Build initial pages and search templates for payroll operations
- Provision user accounts for all 15 licensed users
Owner: Hamza Akhtar
Milestones:
- All four connectors operational and data indexed
- Initial pages built and tested
- All user accounts ready
Read the whole document (2,296 characters)
Phase 3: Testing and Refinement
Timeframe: Week Three (June 2025)
Objectives:
- User acceptance testing with team members
- Refine interface based on feedback
- Validate data accuracy and completeness
Owner: Hamza Akhtar with Daniel Okafor
Milestones:
- Testing sign-off from operations team
- Final page templates approved
- Training materials ready
Phase 4: Go-Live and Handover
Timeframe: Week Four (late June 2025)
Objectives:
- Launch brain to all users in production
- Conduct final user training
- Transition to ongoing support
Owner: Daniel Okafor
Milestones:
- Brain live to all 15 users
- Handover complete and support processes agreed
- First week of support completed
Success Measures
- All 15 users able to log in and ask questions
- Data refresh happening on schedule each business night
- Team using the brain to answer payroll and client queries
Post-Implementation Support
From 1 June 2025, Daniel Okafor will be your dedicated Customer Success Manager. We will conduct a six-monthly check-in to review adoption and value.